Lincoln Park South Play Area Renovation
Updated: August 9, 2024
Summer 2024
Final inspections at Lincoln Park South Play Areas took place the week of July 29, 2024. Lincoln Park Play Area re-opened on August 3, 3034! The construction contract for Westcrest Play Area and Lincoln Park Play Areas was awarded to LW Sunstrom. Construction began the week of January 5, 2024. Westcrest Play Area was complete in March 2024.
Location
Lincoln Park, 8011 Fauntleroy Way SW, 98136
Budget
Seattle Park District provides $600,000 for planning, design and construction.
Schedule
Design: Spring 2021 - Spring 2022
Bid Advertisement/Award: Spring - Summer 2023
Construction: Winter - Summer 2024
Project Description
This improvement project is funded by the Seattle Park District. The play area renovation will update play equipment with play structures accessible to children of all ages and abilities. Additionally, accessibility improvements that meet the standards from the Americans with Disabilities Act (ADA) will be made throughout the play area.
Community Participation
Public Meeting 11/29/2017
Public Meeting 1/24/2018