Madrona Playground Play Area Renovation

Updated: December 17, 2024

Late 2024

Seattle Parks and Recreation issued the Notice to Proceed to Wyser Construction. Wyser will mobilize on-site in mid-December and anticipates completing the project in late spring 2025.

This project will replace the existing play equipment to meet current safety and accessibility standards. The entire play area will be closed throughout construction

Location

Madrona Playground, 3211 E Spring Street, 98122

Budget

The Seattle Park District provides $550,000 for planning, design, and construction.

Schedule

Planning: Spring 2023 - Early 2024
Design: Fall 2023 - Fall 2024
Construction: December 2024

Project Description

This project will replace all of the existing play equipment to meet current safety and accessibility standards. The existing sandbox will be removed to give more space for the adjacent cherry tree grove. This project will also include design support for a structure to provide cover for the adjacent stage, to be built by the community at a future date.

Anticipated Impact: The play area will be closed throughout construction

Community Participation

Thank you to everyone who joined us at our meeting on January 6! Please watch this page for project updates and additional participation opportunities.

Public Meeting - 1/6/24

Public Meeting - 11/4/23

Public Meeting - 9/16/23

Parks and Recreation

AP Diaz, Superintendent
Mailing Address: 100 Dexter Ave N, Seattle, WA, 98109
Phone: (206) 684-4075
Fax: (206) 615-1813
pks_info@seattle.gov

Newsletter Updates

Subscribe

Sign up for the latest updates from Parks and Recreation

Healthy People, Thriving Environment, Vibrant Community