University/Cowen Paving Project
Updated: July 2, 2018
What’s happening now?
In July 2018, we are beginning construction for the University/ Cowen Paving Project. Work is predicted to last 4-5 months and we are working with the community and businesses to minimize construction impacts to the extent feasible. To learn more about the improvements to the street, please read our project factsheet.
We share regular updates via email in addition to distributing flyers in advance of work near affected properties. Sign up to receive project emails. If you have any questions or concerns, please reach out to our project outreach team via email or phone.
Continue reading to learn more about the details of the project and its background.
Overview
University Way NE/Cowen Pl NE is a collector arterial serving approximately 4,000 drivers on an average day and several King County Metro bus routes. Between NE 50th St and NE Ravenna Blvd, University Way NE is a commercial and residential street that supports the University Heights Center, a community P-Patch, shops and restaurants, and the University District Neighborhood Farmers Market on Saturdays.
We identified University Way NE/ Cowen Pl NE as a street that needs to be in better condition to handle both the residential and commercial needs of the community it serves. To make the road safer and resolve user conflicts, the southbound bike lane will be widened, and pedestrian crossings will be improved with the addition of all-way stop signs, marked crosswalks, curb ramps and sidewalk upgrades.
Each year, we pave arterial streets in poor condition to make them safer, smoother, and to extend their useful life. We prioritize paving projects based on pavement condition, traffic volume, geographic equity, cost, and opportunities for grants or coordination with other projects in the area. Repaving streets also creates opportunities to improve street safety and move people and goods more efficiently in a growing Seattle.
Read more about our current paving projects.
Project Description
As part of our paving program, we'll repave approximately 0.5 miles along University Way NE/Cowen Pl NE to make it safer and more comfortable to travel on and to extend the lifespan of the pavement. Paving is an opportunity to cost-effectively update street designs to promote safety, build features called for in citywide transportation plans, and coordinate with other projects. We developed concepts for street designs along these corridors according to the needs of different users and the amount of space available.
In addition to repaving, work also includes curb ramp and sidewalk corner enhancements, spot sidewalk repair, and drainage improvements. University/Cowen will restripe the existing layout and maintain current street operations and design.
We’re also planning to repave 15th Ave NE in 2019, from 55th Ave to Lake City Way NE, which will include street design changes, including protected bike lanes that will connect to the growing northeast Seattle bike network.
History and Background
Since the summer of 2016, we've shared street design concepts with the community and asked how you get around your neighborhood. We sent mailers, offered an online survey, held an open house, dropped off materials, and visited businesses with door-to-door outreach.
We heard from hundreds of people about transportation safety and we appreciate everyone who took time to talk to us. Your feedback helped shape our design proposal for University Way NE and Cowen Pl NE. Here's what we heard from you:
- Concerns about speeding
- Desire to cross street more easily
- Interest in using more transit and biking
- Interest in maintaining parking
- Discourage cut-through traffic
- Desire for turn pockets and signals at key intersections
- Preference for "protected" bike lanes
- Interest in maintaining current operations of the University District Farmers Market
In addition to taking community feedback, we analyzed traffic and parking data and reviewed freight, transit, bike, and pedestrian master plan recommendations. Some of our findings* included:
- Vehicle volumes: 4,000/average day
- Vehicle speed: 29 MPH (85th percentile speed),
- Collisions: 185 in 5 years
- Peak hour parking restrictions: 7-9 AM (southbound) and 4-6 PM (northbound)
*Findings described are for University/Cowen Paving Project. Learn about data for 15th Ave NE paving in the Materials section at the bottom of this page.
Schedule
This is our anticipated project timeline for University/Cowen but dates are subject to change.
Summer/fall 2016
Northeast paving project planning and outreach
Spring 2017
Northeast paving project street concept design and outreach
Summer 2017
Begin University/Cowen design
Summer/fall 2017
Outreach to residents, businesses, and property owners along University/Cowen
Fall 2017
Finish University/Cowen design
Winter 2017/2018
Pre-construction coordination with community for University/Cowen
Winter/spring 2018
Begin University/Cowen construction
Fall 2018
Complete University/Cowen construction
Funding
This project is part of our Arterial and Asphalt and Concrete (AAC) Paving Program. Design and construction of our paving projects, as well as the safety and mobility improvements shown, are funded by the Levy to Move Seattle, approved by Seattle voters in November 2015. We also seek additional funding through grants, when available.
Get Involved
We're committed to engaging with the community throughout the life of the project. We want everyone to have the opportunity to engage with us and ask questions. Outreach is being done throughout the planning, design, and construction phases and here are some of the ways to get involved during the different stages of a project's life:
The Four Stages of Getting Involved
-
Planning
What we do: Collect traffic data, review plans and gather community experiences to define options. -
Design
What we do: Share updates as more details are know. -
Construction
What we do: Provide construction schedule, expected impacts, and a contact for questions. -
Evaluation
What we do: Gather feedback from those that work, live, play and travel near the completed project, and collect traffic data.
- We conducted an online survey to gather feedback about how you travel around your neighborhood and what is working and what's not with these streets.
- We shared draft street design concepts that included what we learned from the survey, as well as pedestrian, bike, freight, and transit master plan recommendations, and traffic data at two open houses.
- We held a public comment period to gather feedback from residents, commuters, and businesses about their ideas on the draft concepts.
- We held stakeholder briefings with our modal advisory boards, businesses, community groups, and schools and visited businesses along the project streets to understand their needs.
June 2016
Seattle Pedestrian Advisory Board presentation
Seattle Bicycle Advisory Board presentation
July 2016
Seattle Freight Advisory Board presentation
October 2016
University District Farmer's Market booth
Hosted Public Open House
November 2016
U-District Livability Open House booth
Door-to-door business outreach
Wedgwood Community Council presentation
Roosevelt High School presentation
December 2016
Seattle Bicycle Advisory Board presentation
May 2017
Ravenna Bryant Community Association presentation
Summer 2017
Begin project design
August 2017
Property owner outreach
February 2018
University District Partnership presentation
March 2018
Pre-construction business survey
April 2018
Pre-construction door to door business outreach
June 2018
Door to door business outreach - distributed construction notices
Materials
To view a PDF of project-related materials, please click on the links provided below.
Outreach materials
- Project factsheet (February 2018)
Project planning
- Final street design concept for 15th Ave NE, University Way NE, Cowen Pl NE (May 2017)
- Northeast Door Hanger (November 2016)
- Northeast Open House Summary (November 2016)
- Northeast Open House Meeting Boards (October 2016)
- Northeast Project Fact Sheet (October 2016)
- Northeast Open House Notice (October 2016)
- Northeast Survey Results Summary (October 2016)
- Northeast Survey Results (September 2016)
- Northeast Paving Survey Notice (August 2016)
Need a translation?
If you need this information translated, please call (206) 256-5458.
Servicios de traducción e interpretación disponibles bajo petición (206) 256-5458.
Matutulungan ka naming maintindihan kung hihingi kang tulong (206) 256-5458.
요청하시면 번역이나 통역을 제공해드립니다 (206) 256-5458.
Dịch và thông dịch viên sẵn sàng nếu có sự yêu cầu (206) 256-5458.
Haddii aad dooneyso turjubeen fadlen wac (206) 256-5458.