Andover and Dakota Pedestrian Safety Enhancements

Updated: July 13, 2023

 This project is complete!

This project was completed in 2023.

Thank you to all who participated in the community prioritization process for this Neighborhood Street Fund project. We completed this community-requested project in 2023!

Final project photos with new curb bulbs and speed cushions

Project Overview

Elements

  • Accessible (ADA) Ramps
  • Curb Bulbs
  • Concrete Panel Replacement
  • Sign and marking updates

Benefits

  • Safety improvements to the intersections will facilitate crossings for people walking and biking
  • New ADA-compliant curb ramps will improve access
  • Curb bulbs have been shown to improve pedestrian crossing safety
  • Speed cushions have been shown to calm traffic speeds

Design

Andover and Dakota Pedestrian Safety Enhancements project map

Safety improvements at intersection of 38th Ave S and S Andover St

Earlier project materials included a marked crosswalk at 38th Ave S and S Andover St. This was an oversight, and the concepts on this page now reflect the proposed design. While a marked crosswalk is not included in the project design, the new curb bulbs and curb ramps will improve access and shorten the crossing distance for people walking and rolling. These improvements will also make people walking and rolling more visible to drivers and encourage slower vehicle speeds on 38th Ave S. Once the curb bulbs are complete, we can monitor this location to see if any additional improvements should be considered.

Project Background

This is one of the 15 Neighborhood Street Fund projects requested by neighbors and selected by the Levy to Move Seattle Oversight Committee. Neighborhood Street Fund is a city program, running on 3-year cycles, that enables neighbors to propose and help prioritize transportation-related projects that are then built by the Seattle Department of Transportation (SDOT). 

Note: funds not used for this project will be returned to the NSF program budget.

Schedule

The NSF program runs on 3-year cycles to select, design, and build projects, but we had project delays this round with design updates and schedule impacts due to SDOT's work responding to the COVID-19 pandemic. The application phase for the 2019-2021 cycle opened October 2018 and projects will be constructed in 2022 and 2023.

NSF timeline

Phase Timeline
Applications 2018
Community Prioritization and Voting 2019
Design 2020
Construction 2022-2023

Questions?

If you have questions or need translated materials, please contact us at NSF_AndoverDakota@seattle.gov or 206-727-3581. Thank you.

Servicios de traducción e interpretación disponibles bajo petición 206-727-3581.

Matutulungan ka naming maintindihan kung hihingi kang tulong 206-727-3581.

요청하시면 번역이나 통역을 제공해드립니다 206-727-3581.

Dịch và thông dịch viên sẵn sàng nếu có sự yêu cầu 206-727-3581.

Haddii aad dooneyso turjubeen fadlen wac 206-727-3581.

Transportation

Greg Spotts, Director
Address: 700 5th Ave, Suite 3800, Seattle, WA, 98104
Mailing Address: PO Box 34996, Seattle, WA, 98124-4996
Phone: (206) 684-7623
684-Road@seattle.gov

Newsletter Updates

Subscribe

Sign up for the latest updates from Transportation

The Seattle Department of Transportation (SDOT) is on a mission to deliver a transportation system that provides safe and affordable access to places and opportunities for everyone as we work to achieve our vision of Seattle as a thriving, equitable community powered by dependable transportation.